Public Update: Joel Lane Beach Access Walkway

Home Posted on September 06, 2022

Joel Lane Beach Access Walkway

The Town of Emerald Isle leadership team secured multiple quotes for the removal and replacement of the Joel Lane Walkway steps. 

Project Funding

    Funds were diverted from other projects to meet the immediate need 

    A Purchase Order was provided on September 1, 2022. 

The lowest and best bid was submitted by B & P Services in the amount of $19,500. 

    Demolition will begin today (September 6). 

    Permits are being secured for the reconstruction of the same.  

    Signage will be placed at the access (by Emerald Isle Parks and Recreation) indicating temporary closure due to construction. 

Construction Timeline

    Construction will commence and take 10-14 days to complete. 

    This timeline is weather dependent and subject to change (without notice). 

The steps will be completely removed and replaced within the existing footprint, to meet CAMA rules on a minor permit. 

Minor adaptations will be needed to comply with current building codes. 



  1. Emerald Isle North Carolina

Contact Us

  1. Town of Emerald Isle
    7500 Emerald Drive
    Emerald Isle, NC 28594

    Phone: 252-354-3424
    Fax: 252-354-5068

Government Websites by CivicPlus®
Arrow Left Arrow Right
Slideshow Left Arrow Slideshow Right Arrow